How many fills, how many days
Machine fills (20 to 100%) per full charge of the unit
| Machine (battery) | NV-M250225 kWh usable | NV-M500450 kWh usable | NV-C1000900 kWh usable | NV-C13001,170 kWh usable | NV-C30002,700 kWh usable | NV-C40003,600 kWh usable · MCS, on study |
|---|
| Develon DX85RE-7 (235 kWh) | 1.1 | 2.3 | 4.5 | 5.9 | 13.6 | |
|---|
| Volvo EWR150 Electric (270 kWh) | 1.0 | 2.0 | 4.0 | 5.1 | 11.9 | |
|---|
| Develon DX160WE-7K (380 kWh) | 0.7 | 1.4 | 2.8 | 3.7 | 8.4 | |
|---|
| Develon DX230LCE-7 (435 kWh) | 0.6 | 1.2 | 2.5 | 3.2 | 7.4 | 9.8 |
|---|
| Volvo A30 Electric (450 kWh) | 0.6 | 1.2 | 2.4 | 3.1 | 7.1 | 9.5 |
|---|
| Develon DX250LCE-7 (570 kWh) | 0.5 | 0.9 | 1.9 | 2.4 | 5.6 | 7.5 |
|---|
| Volvo A40 Electric (540 kWh) | 0.5 | 1.0 | 2.0 | 2.6 | 5.9 | 7.9 |
|---|
| Volvo L120 Electric (282 kWh) | 0.9 | 1.9 | 3.8 | 4.9 | 11.4 | |
|---|
Fill = 80% of the machine's battery, 95% charging efficiency. In grey: less than one fill. Fills add up across machines: 2.0 on an excavator and 2.0 on a dumper means one excavator and one dumper, not two of each. The brands mentioned belong to their respective owners. NV Power Station has no commercial relationship with these manufacturers; their machines are cited as sizing references.
Fleet days covered by one charge
| Fleet (one charge per machine per day) | Energy per day | NV-M250 | NV-M500 | NV-C1000 | NV-C1300 | NV-C3000 | NV-C4000 |
|---|
| 1 excavator (25 t, 435 kWh) | 366 kWh | 0.6 d | 1.2 d | 2.5 d | 3.2 d | 7.4 d | 9.8 d |
|---|
| 1 excavator (25 t) + 1 A30 dumper | 745 kWh | 0.3 d | 0.6 d | 1.2 d | 1.6 d | 3.6 d | 4.8 d |
|---|
| 2 excavators (25 t) + 1 L120 loader | 970 kWh | 0.2 d | 0.5 d | 0.9 d | 1.2 d | 2.8 d | 3.7 d |
|---|
| 3 excavators (25 t) + 2 A30 dumpers | 1,857 kWh | 0.1 d | 0.2 d | 0.5 d | 0.6 d | 1.5 d | 1.9 d |
|---|
| 4 excavators (25 t) + 2 A40 + 2 L120 | 2,850 kWh | 0.1 d | 0.2 d | 0.3 d | 0.4 d | 0.9 d | 1.3 d |
|---|
In grey: the unit does not cover a day on its own; it then works as a buffer, recharged continuously from the grid or a generator set.
Charging time of the unit itself
| Unit | Usable | 63 A (43 kW) | 100 A (70 kW) | 250 A (170 kW) | 400 A (280 kW) | 500 kVA generator set, hybrid |
|---|
| NV-M250 | 225 kWh | 5 h 49 | 3 h 34 | 3 h 34 | 3 h 34 | 3 h 34 |
|---|
| NV-M500 | 450 kWh | 11 h 38 | 7 h 09 | 7 h 09 | 7 h 09 | 7 h 09 |
|---|
| NV-C1000 | 900 kWh | 23 h 15 | 14 h 17 | 5 h 53 | 3 h 34 | 3 h 34 |
|---|
| NV-C1300 | 1,170 kWh | 1.3 d | 18 h 34 | 7 h 39 | 4 h 39 | 4 h 39 |
|---|
| NV-C3000 | 2,700 kWh | 2.9 d | 1.8 d | 17 h 39 | 10 h 43 | 10 h 43 |
|---|
Charging from 0 to 100%; the AC input is limited to 70 kW on the NV-M and 280 kW on the NV-C. The NV-C4000 recharges through its DC input.